Put the revenue and direct costs in one place
Job costing means keeping track of what one job earns and the costs assigned to doing it. Start with revenue, labor, materials, subcontractors, and other direct costs. Compare the estimate with the actual work so you can see what changed.
The calculator below shows the money left after the direct costs you enter. It does not show company net profit. General overhead, financing costs, and taxes are not included. Keep your cost categories consistent and check them against your accounting records.
What to record for each job
| Job detail | Why it matters |
|---|---|
| Job number and agreed work | Connect the estimate, time records, purchases, change orders, and invoice. |
| Revenue | Use the same basis each time, such as the approved invoiced amount excluding sales tax. |
| Labor hours | Record the time assigned to the job. Use a consistent rule for travel and return visits. |
| Full hourly employee cost | Use the hourly labor cost your accounting method assigns to the job, including applicable employer costs such as payroll taxes or benefits. This is often called a loaded labor rate. |
| Materials and subcontractors | Assign purchases and vendor charges to the right job. |
| Other direct costs | Include job-specific rental, disposal, or similar costs without counting the same cost twice. |
| Estimated and actual amounts | Show the difference and explain why it happened. |
If employees have different hourly costs, multiply each person's hours by the applicable rate and add the results. Use an average rate only when it reasonably represents the employees assigned to the job.
How the calculation works
- Direct labor cost = labor hours × full hourly employee cost.
- Total direct job costs = labor + materials + subcontractors + other direct costs.
- Money left after entered direct costs = job revenue − total direct job costs.
- Percentage left after direct costs = money left ÷ job revenue.
The percentage cannot be calculated when revenue is zero, so the calculator marks it unavailable. If you also assign a share of overhead to jobs, show that separately. Do not confuse that different calculation with the direct-cost result shown here.
A worked example
Suppose a service job has $1,200 in revenue, eight labor hours at a full employee cost of $35 per hour, $250 in materials, and $40 in other direct costs. This example has no subcontractor costs.
| Item | Amount |
|---|---|
| Revenue | $1,200 |
| Direct labor: 8 × $35 | $280 |
| Materials | $250 |
| Other direct costs | $40 |
| Total direct job costs | $570 |
| Money left after entered direct costs | $630 |
| Percentage left after direct costs | 52.5% |
These numbers demonstrate the arithmetic. They are not a recommended target, an industry benchmark, or a Service Monkey client result.
Try the job costing calculator
Enter your figures or load the worked example. The calculation runs in your browser. This tool does not send your entries to Service Monkey or save them for a later visit.
Compare the estimate with what happened
When the job records are complete, compare estimated and actual hours, material costs, and revenue. Start with the largest differences. Extra labor might come from an inaccurate estimate, added work, waiting for parts, a return visit, or inconsistent time recording.
Record the explanation beside the difference. If the same problem appears on several jobs, adjust the estimate assumptions or the way the work is organized. Do not count a missing supplier cost as zero just because the invoice has not arrived.
Keep approved changes to the work connected to the job number. Otherwise, a job can appear to have used too many hours when the team actually completed extra authorized work.
Use a short weekly review to improve the next estimate
- Choose a few recently completed jobs with complete records.
- Check that revenue and costs use the same categories.
- Compare estimated and actual hours and direct costs.
- Find the business reason for an important difference.
- Assign the next step: adjust an estimate, change instructions, follow up with a supplier, or clarify the agreed work.
The point of the review is a better decision on the next job. Keep it connected to the work your team is doing.
Common questions
Is the result the same as net profit?
No. The money left after entered direct costs still has to cover costs not assigned to the job. Company overhead, financing costs, and taxes can change the overall result.
Should I record the owner's time?
Record owner involvement consistently so you can see how much work the job consumes. Agree with your accounting professional on how that time should be treated as a cost. Tracking time and recording an accounting expense are different things.
Does this replace my accounting system?
No. Use it as a working sheet for reviewing jobs. Your accounting system remains the place to check actual financial records and cost categories.
Sources and context
These instructions and examples describe a suggested way of working. They are not client case studies or a trade standard. Adapt them to your business and the requirements of your work.